San Diego Quiet Zone

November 27, 2007

CCDC Milestone Schedule - Project milestones include the following

Status   Item
Complete   Conceptual Design, June 2005
Complete   Pedestrian Study, Queuing analysis Study, G Street one-way conversion traffic study, April 2006
Complete   NCTD Quiet Zone policy for Cities in NCTD area - passed by NCTD Board, June 2006
Complete   Design MOU with NCTD up to $250,000.
Complete   Design MOU with NCTD up to $250,000 - Approved by redevelopment Agency, November 2006
Complete   Design contract for MTS (trolley) side south of Broadway with PRE - this contract is directly with the Corporation
Complete   FRA Notice of Intent filed as required by Federal Legislation
25% complete   Status of civil design by RailPros, final design August 2007
25% complete   Status of design of railroad improvements per Design MOU with NCTD, Broadway and north to Laurel Street, final design for August 2007
25% complete   Status of trolley design south of Broadway by PRE, final design August 2007
March 2007   Environmental Review of Quiet Zone - Mitigated Negative Declaration is being publicly circulated for 30-day public and agency review and comment
March 2007   NCTD/MTS/City Legal Agreement - represents 75% of Quiet Zone area
March 2007   BNSF Construction and Maintenance Agreement - represents 25% of Quiet Zone area, complete legal agreement to be finalized by BNSF
April 2007   G Street one-way conversion - Final vote by Redevelopment Agency/City Council
July 2007   Redevelopment Agency/City Council Request to Bid and Funding Authorization, including City maintenance costs
August 2007   Bid Corporation civil and MTS rail work
August 2007   Bid NCTD rail work
August 2007   BNSF needs to start design of their section to meet the September 2008 Quiet Zone implementation date. The BNSF Legal Agreement requires one year from signing for design and construction to completion.
November 2007   Award Bid and order material for Corporation constructed civil work (such as medians, traffic signals and G Street one-way conversion)
November 2007   Award Bid and order material with long lead times (six months) of Corporation constructed MTS rail work - south of Broadway.
November 2007   Award Bid and order material with long lead times (six months) of NCTD constructed NCTD/MTS rail work (Broadway and north).
March 2008   Start construction of civil work
April 2008   Start construction of MTS rail work south of Broadway
April 2008   Start construction of NCTD/MTS rail work.
July - Sep 2008   Quiet Zone completed